Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   For the network shown in the given figure, t... Start Learning for Free
For the network shown in the given figure, the expected completion time of the project is
  • a)
    26 days
  • b)
    27 days
  • c)
    30 days
  • d)
    indeterminable
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
For the network shown in the given figure, the expected completion ti...
Paths are: 1-2-6-8 = 18
1-2-3-4-5-6-8 = 30
1-2-3-4-5-8 = 27
1-2-3-4-7-8 = 26
1-3-4-5-6-8 = 25
1-3-4-5-8 = 22
1-3-4-7-8 = 21
1-4-5-6-8 = 24
1-4-5-8 = 21
1-4-7-8 = 20
View all questions of this test
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer?
Question Description
For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer?.
Solutions for For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For the network shown in the given figure, the expected completion time of the project isa) 26 daysb) 27 daysc) 30 daysd) indeterminableCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev