Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   The earliest occurrence time for event '1' i... Start Learning for Free
The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.
If the activity time is 11 weeks, then the total float will be
  • a)
    11
  • b)
    13
  • c)
    18
  • d)
    24
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The earliest occurrence time for event '1' is 8 weeks and the latest ...
Total float = 37 − 8 − 11 = 18 days
View all questions of this test
Most Upvoted Answer
The earliest occurrence time for event '1' is 8 weeks and the latest ...
Calculation of Total Float:

Given data:
- Earliest occurrence time for event '1': 8 weeks
- Latest occurrence time for event '1': 26 weeks
- Earliest occurrence time for event '2': 32 weeks
- Latest occurrence time for event '2': 37 weeks
- Activity time: 11 weeks

Calculation:
1. Calculate the total float for event '1':
Total float for event '1' = Latest occurrence time for event '1' - Earliest occurrence time for event '1' - Activity time
Total float for event '1' = 26 weeks - 8 weeks - 11 weeks = 7 weeks
2. Calculate the total float for event '2':
Total float for event '2' = Latest occurrence time for event '2' - Earliest occurrence time for event '2' - Activity time
Total float for event '2' = 37 weeks - 32 weeks - 11 weeks = 18 weeks

Conclusion:
The total float is the minimum of the total float for event '1' and event '2'. Therefore, the total float is 18 weeks. Hence, the correct answer is option 'C'.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer?
Question Description
The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer?.
Solutions for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer?, a detailed solution for The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The earliest occurrence time for event '1' is 8 weeks and the latest occurrence time for event' 1' is 26 weeks. The earliest occurrence time for event '2' is 32 weeks and the latest occurrence time for event '2' is 37 weeks.If the activity time is 11 weeks, then the total float will bea) 11b) 13c) 18d) 24Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev