Solve the following question and mark the best possible option.X, Y an...
Assume the total work to be 1200 units. (LCM of all the numbers)
Then Z’s 1 day work = 8 units.
⇒ (X + Y + Z)’s 1 day work = 40 units.
X, Y, Z work together in the first 4 days
⇒Work done in the first 4 days = 40 × 4 = 160 units
Z alone works during the last 80 days
⇒Work done in the last 80 days = 80 × 8 = 640 units
Remaining work = 1200 – (160 + 640) = 400 units
This work is done by Y and Z in 20 days.
⇒ (Y + Z)’s 1 day work = 20 units
⇒X’s 1 day work = (X + Y + Z)’s 1 day work – (Y + Z)’s 1 day work = 40 units – 20 units = 20 units
⇒X can do the work of 1200 units in 60 days.
View all questions of this test
Solve the following question and mark the best possible option.X, Y an...
To solve this question, let's first determine the work efficiency of each person. Since X, Y, and Z can complete the work together in 30 days, their combined efficiency per day is 1/30.
Let's assume that X's efficiency per day is x, Y's efficiency per day is y, and Z's efficiency per day is z.
1. Work done by X, Y, and Z in 4 days:
Since they work together for 4 days, the total work done by them is (1/30) * 4 = 4/30.
2. Work done by Y and Z in 20 days:
After X leaves, Y and Z continue the work. So, their combined efficiency per day is (y + z). Therefore, the work done by Y and Z in 20 days is (y + z) * 20.
3. Work done by Z in 80 days:
After Y leaves, Z works alone. So, the work done by Z in 80 days is z * 80.
Now, let's determine the remaining work that X needs to complete alone.
Remaining work = Total work - Work done by X, Y, and Z in 4 days - Work done by Y and Z in 20 days - Work done by Z in 80 days
Remaining work = 1 - 4/30 - (y + z) * 20 - z * 80
Since Z can complete the work alone in 150 days, his efficiency per day is 1/150. Therefore, z = 1/150.
Substituting the value of z in the equation for remaining work:
Remaining work = 1 - 4/30 - (y + 1/150) * 20 - 1/150 * 80
Simplifying the equation, we get:
Remaining work = 1 - 2/15 - (y + 1/150) * 2 - 4/75
Now, we know that the remaining work needs to be completed by X alone. So, the equation becomes:
Remaining work = x * D
where D is the number of days X takes to complete the remaining work.
Substituting the value of remaining work in the equation:
x * D = 1 - 2/15 - (y + 1/150) * 2 - 4/75
Now, we need to find the value of D, which represents the number of days X takes to complete the work. To do that, we need to know the value of x and y, which are not given in the question.
Therefore, the given information is insufficient to determine the number of days X takes to complete the work.
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.