The following data is observed for a casting process:
Mass of casting = 5000 kg
Density of metal = 8000 kg/m3
Pouring time = 10 sec
Efficiency factor = 0.9
Effective had = 2 m
The chock area of the casting is ___________mm2
  • a)
    11050
  • b)
    11120
Correct answer is between ' 11050, 11120'. Can you explain this answer?
Most Upvoted Answer
The following data is observed for a casting process:Mass of casting ...
= 0.01108595 m2
= 11085.95 mm2
Free Test
Community Answer
The following data is observed for a casting process:Mass of casting ...
= 0.01108595 m2
= 11085.95 mm2
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer?.
Solutions for The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer?, a detailed solution for The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? has been provided alongside types of The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The following data is observed for a casting process:Mass of casting = 5000 kgDensity of metal = 8000 kg/m3Pouring time = 10 secEfficiency factor = 0.9Effective had = 2 mThe chock area of the casting is ___________mm2a) 11050b) 11120Correct answer is between ' 11050, 11120'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev