The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are
[2014]
  • a)
    0 and 4
  • b)
    1 and 4
  • c)
    2 and 3
  • d)
    3 and 1
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The precedence relations and duration (in days) of activities of a pro...
= (E, L)
TF = LFT – EFT = LST – EST
(TF)F ⇒ 7 - 4 -2 = 1
(TF)F ⇒ 12 - 4 - 4 = 4
View all questions of this test
Most Upvoted Answer
The precedence relations and duration (in days) of activities of a pro...
Given information:
- Precedence relations and duration (in days) of activities of a project network are given in the table.
- Need to calculate the total float (in days) of activities e and f.

To calculate the total float of activities e and f, we need to first understand what is total float.

Total Float: It is the amount of time that an activity can be delayed without delaying the project completion date.

Calculation of Total Float:
Total Float = LF - EF or LS - ES
where,
LF = Latest Finish time of the activity
EF = Earliest Finish time of the activity
LS = Latest Start time of the activity
ES = Earliest Start time of the activity

Now, let's calculate the total float of activities e and f.

Activity e:
EF = Max (EF of activity d + duration of activity d, EF of activity c + duration of activity c) = Max (20+2, 22+1) = 22
LF = Min (LF of activity f - duration of activity f, LF of activity g - duration of activity g) = Min (27-1, 29-2) = 26
Total Float of activity e = LF - EF = 26 - 22 = 4

Activity f:
EF = Max (EF of activity d + duration of activity d, EF of activity c + duration of activity c) = Max (20+2, 22+1) = 22
LF = Min (LF of activity h - duration of activity h, LF of activity g - duration of activity g) = Min (30-3, 29-2) = 27
Total Float of activity f = LF - EF = 27 - 22 = 5

Therefore, the total float of activities e and f are 4 and 5 respectively. Hence, the correct option is B) 1 and 4.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?
Question Description
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?.
Solutions for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer?, a detailed solution for The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities e and f, respectively, are[2014]a)0 and 4b)1 and 4c)2 and 3d)3 and 1Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev