Consider the following statements In the bar chart planning
1. Interdependence of the operations cannot be portrayed
2. Progress of work can be measured
3. Spare time of the activities can be determined
4. Schedule cannot be updated.​
Which of these statements is/are correct?
  • a)
    1, 2 and 3
  • b)
    1 and 4
  • c)
    2, 3 and 4
  • d)
    1, 2 and 4
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Consider the following statements In the bar chart planning1. Interdep...
Explanation:

Bar chart planning is a graphical representation of a project schedule. It shows the activities of a project, their duration, and the interrelations between them. The following statements are given about bar chart planning:

1. Interdependence of the operations cannot be portrayed: This statement is correct. Bar chart planning only shows the activities and their duration. It does not show the interdependence of the operations.

2. Progress of work can be measured: This statement is correct. Bar chart planning helps to measure the progress of work by comparing the actual progress with the planned progress.

3. Spare time of the activities can be determined: This statement is correct. Bar chart planning helps to determine the spare time of the activities, which can be used to improve the efficiency of the project.

4. Schedule cannot be updated: This statement is incorrect. Bar chart planning can be updated to reflect changes in the project schedule.

Therefore, the correct option is 'B' as only statement 1 and 4 are correct.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer?
Question Description
Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer?.
Solutions for Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements In the bar chart planning1. Interdependence of the operations cannot be portrayed2. Progress of work can be measured3. Spare time of the activities can be determined4. Schedule cannot be updated.Which of these statements is/are correct?a)1, 2 and 3b)1 and 4c)2, 3 and 4d)1, 2 and 4Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev