In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph?
Most Upvoted Answer
In routing a flood theough a reach the point of intersection of inflow...
Interception Point of Inflow and Outflow Hydrographs
To understand why the point of intersection of the inflow and outflow hydrographs coincides with the peak of the outflow hydrograph during flood routing, we need to consider the following key points:

Inflow and Outflow Hydrographs
- The inflow hydrograph represents the rate of flow entering a reach, while the outflow hydrograph represents the rate of flow leaving the reach.
- During flood routing, the goal is to determine how the inflow hydrograph transforms as it passes through the reach and results in the outflow hydrograph.

Peak of Outflow Hydrograph
- The peak of the outflow hydrograph occurs when the maximum flow rate is observed at the downstream end of the reach.
- This peak flow rate is influenced by factors such as the volume of water entering the reach, the channel characteristics, and the routing parameters.

Intersection Point of Inflow and Outflow Hydrographs
- The point of intersection of the inflow and outflow hydrographs occurs when the rate of inflow entering the reach equals the rate of outflow leaving the reach.
- This point signifies a balance between the volume of water entering the reach and the capacity of the reach to convey that water downstream.
- During flood routing, as the inflow hydrograph rises and falls, it eventually intersects with the rising limb of the outflow hydrograph at the peak flow rate.
Therefore, the point of intersection of the inflow and outflow hydrographs coincides with the peak of the outflow hydrograph during flood routing due to the balance between inflow and outflow rates at that specific moment in time.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph?
Question Description
In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph?.
Solutions for In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? defined & explained in the simplest way possible. Besides giving the explanation of In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph?, a detailed solution for In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? has been provided alongside types of In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? theory, EduRev gives you an ample number of questions to practice In routing a flood theough a reach the point of intersection of inflow ans outflow hudeogrph coincides with the peak of outflow hydrograph? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev