Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The drawdown, corresponding to a steady disch... Start Learning for Free
The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______
  • a)
    pumping out test
  • b)
    pumping in test
  • c)
    constant head permeability test
  • d)
    falling head permeability test
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
The drawdown, corresponding to a steady discharge, are observed at a n...
The permeability can be determined by pumping out test. Pumping must continue at a uniform rate for a sufficient time to approach a steady state condition.
View all questions of this test
Most Upvoted Answer
The drawdown, corresponding to a steady discharge, are observed at a n...
Drawdown in Pumping Out Test

In a pumping out test, the drawdowns are observed at a number of wells. This test is conducted to determine the yield and efficiency of a well or a group of wells. The following are the details of the pumping out test:

Procedure:

1. A well is pumped at a constant rate, and the water level is measured at a number of observation wells located at different distances from the pumping well.

2. The water level in each observation well is measured several times during the test, and the drawdown corresponding to each measurement is recorded.

3. The test is continued until the water level in the pumping well stabilizes, and the drawdown at the observation wells reaches a constant value.

4. The data obtained from the test is used to plot a drawdown-time curve, which is used to determine the yield and efficiency of the well.

Interpretation:

The drawdown-time curve obtained from the pumping out test provides information about the hydraulic properties of the aquifer. The following are the interpretations that can be made from the curve:

1. The yield of the well can be determined from the maximum drawdown observed during the test.

2. The efficiency of the well can be determined from the slope of the curve during the early part of the test.

3. The hydraulic conductivity of the aquifer can be determined from the shape of the curve and the distance between the pumping well and the observation wells.

Conclusion:

The pumping out test is an important tool for determining the yield and efficiency of a well or a group of wells. The drawdowns observed at the observation wells provide valuable information about the hydraulic properties of the aquifer, which can be used to optimize the design and operation of the wells.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer?
Question Description
The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The drawdown, corresponding to a steady discharge, are observed at a number of wells in _______a)pumping out testb)pumping in testc)constant head permeability testd)falling head permeability testCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev