Consider the following statements:

In the critical path method of construction planning. Free float can be

1. Greater than total float

2. Greater than Independent Float

3. Equal to Total Float

4. Less than Independent Float

Float Of these statements

  • a)
    1 and 4 are correct

  • b)
    2 and 3 are correct

  • c)
    3 and 4 are correct

  • d)
    1 and 2 are correct

Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Consider the following statements:In the critical path method of const...
The critical path is the sequence of activities that represents the longest path through a project. It determines the shortest possible project duration.


The critical path can be easily determined with the help of total float calculations. The activities on the critical path are those activities that have total float equal to zero


i.e. TF = 0.


Independent Float



  • It refers to the amount of time by which the start of an activity is can be delayed without affecting EST of any immediately following activity

  • It is given by IF = FF – S 

  • i.e. FF = IF + Si

  • If S= 0 → FF = IF = 0

  • If S≠ 0 FF > IF

View all questions of this test
Most Upvoted Answer
Consider the following statements:In the critical path method of const...
Explanation:

Critical Path Method (CPM) is a project management technique used to determine the longest possible route to complete a project, identify the activities that depend on each other, and estimate the duration of the project. The CPM is based on the concept of float, which refers to the amount of time an activity can be delayed without delaying the entire project.

Total Float: Total float is the amount of time an activity can be delayed without delaying the project completion date. It is calculated as the difference between the late finish date and the early finish date of an activity.

Free Float: Free float is the amount of time an activity can be delayed without delaying the early start date of its successor activity. It is calculated as the difference between the early finish date of an activity and the early start date of its successor activity minus one.

Independent Float: Independent float is the amount of time an activity can be delayed without delaying the early start date of any other activity. It is the difference between the early start date of an activity and the late start date of its predecessor activity minus one.

Based on the above definitions, the correct statement is:

b) 2 and 3 are correct

Explanation of each statement:

1. Greater than total float: Free float can never be greater than total float because total float includes free float plus any additional time that an activity can be delayed without affecting the start of its successor activity.

2. Greater than Independent Float: Free float can be greater than independent float because independent float takes into account the delay of the predecessor activity, while free float only considers the delay of the successor activity.

3. Equal to Total Float: Free float can never be equal to total float because total float includes free float plus any additional time that an activity can be delayed without affecting the start of its successor activity.

4. Less than Independent Float: Free float can never be less than independent float because independent float takes into account the delay of the predecessor activity, while free float only considers the delay of the successor activity.

In summary, the correct statement is 2 and 3 are correct.
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer?
Question Description
Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements:In the critical path method of construction planning. Free float can be1. Greater than total float2. Greater than Independent Float3. Equal to Total Float4. Less than Independent FloatFloat Of these statementsa)1 and 4 are correctb)2 and 3 are correctc)3 and 4 are correctd)1 and 2 are correctCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev