Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   If critical ratio is a) the job is behind sc... Start Learning for Free
If critical ratio is < 1="" />
  • a)
    the job is behind schedule
  • b)
    the job is on schedule
  • c)
    the job is ahead of schedule
  • d)
    None
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
If critical ratio is a) the job is behind scheduleb) the job is on sc...
Explanation:

Critical ratio is a measure of the urgency of a job that needs to be completed. It is defined as the ratio of time remaining until the deadline to the time required to complete the job.

If the critical ratio is less than 1, it means that the time remaining until the deadline is less than the time required to complete the job. In this case, the job is behind schedule and needs to be expedited.

If the critical ratio is equal to 1, it means that the time remaining until the deadline is exactly equal to the time required to complete the job. In this case, the job is on schedule.

If the critical ratio is greater than 1, it means that the time remaining until the deadline is more than the time required to complete the job. In this case, the job is ahead of schedule and can be delayed if necessary.

Therefore, the correct answer is option 'A', which states that if the critical ratio is less than 1, the job is behind schedule.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer?.
Solutions for If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If critical ratio is a) the job is behind scheduleb) the job is on schedulec) the job is ahead of scheduled) NoneCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev