Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  In time-cost optimization of a project, crash... Start Learning for Free
In time-cost optimization of a project, crashing is done
  • a)
    on all the activities
  • b)
    on all the activities lying on the critical paths
  • c)
    only on activities lying on the original critical path and having flatter cost slopes
  • d)
    on original critical activities and those that become critical
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
In time-cost optimization of a project, crashing is donea)on all the a...
Crashing is a technique used in project management to shorten the project duration by reducing the time required for certain activities. It involves adding additional resources or increasing the intensity of work on specific activities to accelerate their completion. Time-cost optimization aims to find the most cost-effective way to reduce the project duration while meeting the project objectives.

In time-cost optimization, crashing is not done on all activities indiscriminately. Instead, it is focused on specific activities that lie on the original critical path and have flatter cost slopes. The original critical path refers to the sequence of activities that determine the longest duration of the project. Activities on the critical path have zero slack or float, meaning any delay in their completion would cause a delay in the overall project.

Below are the explanations for the given options:

a) Crashing on all the activities: This option is not correct because crashing is not done on all activities. It is focused on specific activities.

b) Crashing on all the activities lying on the critical paths: This option is also not correct because crashing is not done on all activities lying on the critical paths. Only activities on the original critical path and those that become critical after crashing are considered.

c) Crashing only on activities lying on the original critical path and having flatter cost slopes: This option is correct. Crashing is done on activities that lie on the original critical path. These activities are crucial for determining the project duration. Additionally, activities with flatter cost slopes are preferred for crashing because they offer better cost-effectiveness.

d) Crashing on original critical activities and those that become critical: This option is incorrect because crashing is not done on all activities that become critical after crashing. Only activities on the original critical path and those that become critical after crashing are considered.

In summary, crashing is focused on activities lying on the original critical path and having flatter cost slopes. These activities are crucial for determining the project duration and offer better cost-effectiveness when crashed.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer?
Question Description
In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer?.
Solutions for In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In time-cost optimization of a project, crashing is donea)on all the activitiesb)on all the activities lying on the critical pathsc)only on activities lying on the original critical path and having flatter cost slopesd)on original critical activities and those that become criticalCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev