Question Description
A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared
according to
the Railways exam syllabus. Information about A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways.
Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice A does 60% of the work in 45 days. He then calls B, and they together finish the remaining work in 18 days. How long B alone would take to do the whole work?a)120.5 daysb)118.5 daysc)125 daysd)112.5 dayCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Railways tests.