Railways Exam  >  Railways Questions  >   A fixed stipulated sum of penalty payable by... Start Learning for Free
A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?
  • a)
    Compensatory payment
  • b)
    Liquidated damage
  • c)
    Fixed penalty
  • d)
    Damage charge
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
A fixed stipulated sum of penalty payable by the contractor having no...
Liquidated damages: These are damages defined in the construction contract and chargeable against funds due to the contractor for each day the contractor fails to complete the project beyond the contract completion date.
Free Test
Community Answer
A fixed stipulated sum of penalty payable by the contractor having no...
Liquidated damages

Liquidated damages are a fixed stipulated sum of penalty payable by the contractor having no relationship with real damage. It is a predetermined amount of compensation agreed upon by both parties at the time of contract signing, which the contractor will pay in case of any delay or breach of contract.

Purpose

The purpose of liquidated damages is to compensate the owner for the losses incurred due to the contractor's default, delay or breach of contract. It also provides certainty and predictability in terms of the amount of compensation to be paid by the contractor in case of default.

Calculation

Liquidated damages are calculated based on the time of delay and the value of the contract. The amount of liquidated damages is usually a percentage of the contract value per day of delay. For example, if the contract value is $1 million and the liquidated damages are set at 0.1% per day, the contractor would have to pay $1,000 per day of delay.

Enforcement

Liquidated damages are enforceable only if they are reasonable and do not exceed the actual losses incurred by the owner due to the contractor's default. If the liquidated damages are found to be excessive or punitive, they may be considered unenforceable.

Conclusion

In summary, liquidated damages are a predetermined amount of compensation agreed upon by both parties at the time of contract signing, which the contractor will pay in case of any delay or breach of contract. It provides certainty and predictability in terms of the amount of compensation to be paid by the contractor in case of default.
Explore Courses for Railways exam
Question Description
A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? for Railways 2025 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Railways 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A fixed stipulated sum of penalty payable by the contractor having no relationship with real damage is known as?a)Compensatory paymentb)Liquidated damagec)Fixed penaltyd)Damage chargeCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam
Signup to solve all Doubts
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev