In CPM network critical path denotes the
  • a)
    path where maximum resources are used
  • b)
    path where minimum resources are used
  • c)
    path where delay of one activity prolongs the duration of completion of project
  • d)
    path that gets monitored automatically
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
In CPM network critical path denotes thea)path where maximum resources...
In a CPM (Critical Path Method) network, the critical path refers to the sequence of activities that determines the total duration of the project. It is the longest path through the network and represents the minimum time required to complete the project.

The critical path is determined based on the dependencies and durations of each activity in the project. Activities are represented by nodes in the network, and the arrows between the nodes indicate the dependencies between them. The duration of each activity is also specified.

Now, let's discuss the options given in the question and why option 'C' is the correct answer:

a) Path where maximum resources are used:
The critical path does not necessarily involve the maximum utilization of resources. It is possible that activities on the critical path require fewer resources compared to other paths in the network.

b) Path where minimum resources are used:
Similar to the previous option, the critical path does not focus on minimizing resource utilization. It is primarily concerned with determining the duration of the project based on the dependencies and durations of activities.

c) Path where delay of one activity prolongs the duration of completion of the project:
This is the correct answer. The critical path is the one where any delay in the completion of an activity will directly impact the overall project completion time. Each activity on the critical path has zero total float, which means there is no flexibility or slack in their scheduling. Any delay in these activities will extend the project duration.

d) Path that gets monitored automatically:
While the critical path is an important aspect of project management, it does not necessarily mean that it gets monitored automatically. Monitoring the critical path requires tracking the progress of activities, identifying any delays or bottlenecks, and making necessary adjustments to ensure timely project completion.

Overall, the critical path plays a crucial role in project planning and scheduling. It helps project managers to identify the activities that are most critical to the project's duration and ensure that they are completed on time to prevent project delays.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?
Question Description
In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?.
Solutions for In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In CPM network critical path denotes thea)path where maximum resources are usedb)path where minimum resources are usedc)path where delay of one activity prolongs the duration of completion of projectd)path that gets monitored automaticallyCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev