Railways Exam  >  Railways Questions  >   The critical path of a network representsa)T... Start Learning for Free
The critical path of a network represents
  • a)
    The maximum time required for completion of a project
  • b)
    The minimum time required for completion of a project
  • c)
    The maximum cost required for completion of a project
  • d)
    The minimum cost required for completion of a project
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
The critical path of a network representsa)The maximum time required ...
From the activity network representation, it can be analysed that the minimum time to complete the project is the maximum of all paths from start to finish.
So, the longest path will represent the critical path for the network, and it will represent the minimum possible duration required to complete the project.
The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.
View all questions of this test
Most Upvoted Answer
The critical path of a network representsa)The maximum time required ...
The critical path of a network represents the minimum time required for completion of a project.

Understanding Critical Path

The critical path is a method used in project management to determine the tasks or activities that are critical to the completion of a project. It represents the longest duration path through a network diagram, which consists of all the dependent tasks and their respective durations. The critical path helps project managers identify the tasks that must be completed on time in order to prevent delays in the overall project completion.

Calculating Critical Path

To calculate the critical path, project managers analyze the network diagram and determine the earliest start and finish times for each task. The earliest start time is the earliest possible time at which a task can begin, considering all its predecessor tasks. The earliest finish time is the earliest time at which a task can be completed, considering its duration and the earliest start time.

Once the earliest start and finish times are determined for each task, project managers move on to calculate the latest start and finish times. The latest finish time is the latest possible time at which a task can be completed without delaying the project. The latest start time is the latest possible time at which a task can start without delaying the project.

Identifying the Critical Path

By comparing the earliest and latest start and finish times, project managers can identify the critical path. The critical path is the sequence of tasks that have the same earliest start and finish times as their latest start and finish times. This means that any delay in the tasks on the critical path will directly impact the overall project completion time.

Importance of the Critical Path

The critical path is important in project management because it helps project managers prioritize tasks and allocate resources effectively. By focusing on the critical path tasks, project managers can ensure that these activities are completed on time, minimizing the risk of project delays. Additionally, the critical path allows project managers to determine the project's total duration and make informed decisions regarding project scheduling and resource allocation.

Overall, the critical path represents the minimum time required for completion of a project. It helps project managers identify the tasks that are crucial to the project's success and enables them to effectively manage and control the project timeline.
Explore Courses for Railways exam
The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer?
Question Description
The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The critical path of a network representsa)The maximum time required for completion of a projectb)The minimum time required for completion of a projectc)The maximum cost required for completion of a projectd)The minimum cost required for completion of a projectCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev