Current Affairs Exam  >  Current Affairs Questions  >  With reference to the Electricity (Transmissi... Start Learning for Free
With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:
1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.
2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.
Which of the statements given above is/are correct?
  • a)
    1 only
  • b)
    2 only
  • c)
    Both 1 and 2
  • d)
    Neither 1 nor 2
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
With reference to the Electricity (Transmission System Planning, Devel...
The Union Ministry of Power has promulgated the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021.
  • The rules underpin a system of transmission access which is termed as a General Network Access in the inter-state transmission system.
  • This provides flexibility to the States as well as the generating stations to acquire, hold and transfer transmission capacity as per their requirements. Thus, the rules will bring in rationality, responsibility and fairness in the process of transmission planning as well as its costs.
  • In a major change from the present system of taking transmission access, power plants will not have to specify their target beneficiaries.
  • The rules will also empower state power distribution and transmission companies to determine their transmission requirements and build them.
  • Also, states will be able to purchase electricity from short term and medium term contracts and optimize their power purchase costs. Apart from introducing GNA, the rules also specify clear roles of various agencies involved in the transmission planning process.
  • The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.
  • The rules have enabled, for the first time, that the transmission capacity can be sold, shared or purchased by the States and generators.
  • Hence both statements are correct.
Attention Current Affairs Students!
To make sure you are not studying endlessly, EduRev has designed Current Affairs study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Current Affairs.
Explore Courses for Current Affairs exam

Similar Current Affairs Doubts

Top Courses for Current Affairs

With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?
Question Description
With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? for Current Affairs 2024 is part of Current Affairs preparation. The Question and answers have been prepared according to the Current Affairs exam syllabus. Information about With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Current Affairs 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?.
Solutions for With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Current Affairs. Download more important topics, notes, lectures and mock test series for Current Affairs Exam by signing up for free.
Here you can find the meaning of With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?, a detailed solution for With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice With reference to the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021, consider the following statements:1. It empower state power distribution and transmission companies to determine their transmission requirements and build them.2. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Current Affairs tests.
Explore Courses for Current Affairs exam

Top Courses for Current Affairs

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev