Current Affairs Exam  >  Current Affairs Questions  >  With reference to the Battery Energy Storage ... Start Learning for Free
With reference to the Battery Energy Storage System (BESS), consider the following statements:
1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.
2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.
Which of the statements given above is/are correct?
  • a)
    1 only
  • b)
    2 only
  • c)
    Both 1 and 2
  • d)
    Neither 1 nor 2
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
With reference to the Battery Energy Storage System (BESS), consider t...
Government has given go ahead for inviting the expression of interest for installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project.
  • This is the joint effort of both Ministry of New and renewable energy and Ministry of Power who have been working on this to provide a road map for the installation of the energy storage system in the country.
  • Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.
  • This will be published along with the RFS bid document and the draft comprehensive guideline for procurement and utilization of BESS as a part of generation, transmission and distribution assets and with all ancillary services.
  • Based on the suggestions and the feedback from various stakeholders, the final RFS document will be floated in the first week of November 2021, along with the final comprehensive guidelines for procurement and utilization of BESS as a part of generation, transmission and distribution assets and with all ancillary services.
Going forward, India plans to use energy storage system under following business cases:
  • Renewable energy along with the energy storage system
  • Energy storage system as grid element to maximize the use of transmission system and strengthening grid stability and also to save investment in the augmentation of transmission infrastructure.
  • Storage as an asset for balancing services and flexible operation. The system operator i.e. load dispatchers (RLDCs and SLDCs) may use storage system for frequency control and balancing services to manage the inherent uncertainty/variations in the load due to un-generation.
  • Storage for distribution system i.e. it may be placed at the load centre to manage its peak load and other obligations.
  • As a merchant capacity by the energy storage system developer and sell in the power market
  • Any other future business models as a combination of the above.
  • Hence both statements are correct.
View all questions of this test
Most Upvoted Answer
With reference to the Battery Energy Storage System (BESS), consider t...
Statement 1: Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.

Statement 2: Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.

To determine the correctness of the statements, let's analyze each statement individually:

Statement 1: Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.

The statement suggests that SECI has invited expressions of interest for the procurement of 1000 MWh Battery Energy Storage System (BESS). This indicates that SECI is actively seeking to acquire a BESS for its operations. As SECI is indeed a CPSU (Central Public Sector Undertaking) under the Ministry of New and Renewable Energy, this statement is correct.

Statement 2: Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.

The statement claims that the installation of a 1000 MWh BESS as a pilot project is a collaborative effort between the Ministry of New and Renewable Energy and the Ministry of Power. To verify this, we need to examine whether both ministries are involved in this project.

It is important to note that the Ministry of Power in India is responsible for the development of policies and programs related to the power sector, while the Ministry of New and Renewable Energy focuses on renewable energy sources. Since the installation of a BESS involves both power management and renewable energy integration, it is plausible that both ministries would be involved in such a project. Therefore, statement 2 is also correct.

In conclusion, both statements 1 and 2 are correct. SECI, a CPSU under the Ministry of New and Renewable Energy, has called for the expression of interest for procurement of 1000 MWh BESS, and the installation of this BESS as a pilot project is a joint effort of both the Ministry of New and Renewable Energy and the Ministry of Power.
Attention Current Affairs Students!
To make sure you are not studying endlessly, EduRev has designed Current Affairs study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Current Affairs.
Explore Courses for Current Affairs exam

Top Courses for Current Affairs

With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?
Question Description
With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? for Current Affairs 2024 is part of Current Affairs preparation. The Question and answers have been prepared according to the Current Affairs exam syllabus. Information about With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Current Affairs 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?.
Solutions for With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Current Affairs. Download more important topics, notes, lectures and mock test series for Current Affairs Exam by signing up for free.
Here you can find the meaning of With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer?, a detailed solution for With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice With reference to the Battery Energy Storage System (BESS), consider the following statements:1. Solar Energy Corporation of India (SECI), a CPSU under Ministry of New and renewable energy, has called for the expression of interest for procurement of 1000 MWh BESS.2. Installation of 1000 MWh Battery Energy Storage System (BESS) as a pilot project is the joint effort of both Ministry of New and renewable energy and Ministry of Power.Which of the statements given above is/are correct?a)1 onlyb)2 onlyc)Both 1 and 2d)Neither 1 nor 2Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Current Affairs tests.
Explore Courses for Current Affairs exam

Top Courses for Current Affairs

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev