A and B together can do a works in 12 days. B and C together do it in 15 days. If A's efficiency is twice that of C, then the days required for B alone to finish the work is
  • a)
    60
  • b)
    30
  • c)
    20
  • d)
    15
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A and B together can do a works in 12 days. B and C together do it in ...
Given information:
- A and B together can do a work in 12 days.
- B and C together can do the same work in 15 days.
- Efficiency of A is twice that of C.

Let's assume that the total work is 60 units (LCM of 12 and 15).
- So, A and B together can do 5 units of work in a day (60/12 = 5).
- And, B and C together can do 4 units of work in a day (60/15 = 4).

Let's represent the efficiency of C as x units of work per day.
- So, the efficiency of A will be 2x units of work per day (as given).
- Therefore, the efficiency of B will be (5 - 2x) units of work per day (since A and B together can do 5 units of work in a day).

Now, let's apply the concept of work and efficiency to find the time taken by B alone to do the work.
- A and B together can do 2x + (5 - 2x) = 5 units of work in a day.
- Therefore, the efficiency of C will be x = 5/2 units of work per day.
- And, the efficiency of B will be (5 - 2x) = 5 - (5/2) = 5/2 units of work per day.
- So, B alone can do (5/2) units of work in a day.
- Therefore, B alone will take (60/(5/2)) = 24 days to finish the work.

Hence, the correct answer is option C (20 days).
Free Test
Community Answer
A and B together can do a works in 12 days. B and C together do it in ...
A and B will do in 1 day, 1/12​ amount of work
B and C will do in 1 day, 1/15​ amount of work
Hence adding up above two equations
A + 2B + C will do in 1 day, 9/60 amount of work
as it is mentioned A = 2C (i.e. efficiency of A is twice of C)
So 2C + 2B + C will do in 1 day 9/60 amount of work
or 2(B+C) + C = 9/60
or C = 1/60​ (as B + C = 1/15)

So B alone will do work in 20 days.
Explore Courses for SSC CGL exam

Top Courses for SSC CGL

A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer?
Question Description
A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? for SSC CGL 2024 is part of SSC CGL preparation. The Question and answers have been prepared according to the SSC CGL exam syllabus. Information about A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for SSC CGL 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer?.
Solutions for A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for SSC CGL. Download more important topics, notes, lectures and mock test series for SSC CGL Exam by signing up for free.
Here you can find the meaning of A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer?, a detailed solution for A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B together can do a works in 12 days. B and C together do it in 15 days. If As efficiency is twice that of C, then the days required for B alone to finish the work isa)60b)30c)20d)15Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice SSC CGL tests.
Explore Courses for SSC CGL exam

Top Courses for SSC CGL

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev