Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >   In a three-phase signal system design for a ... Start Learning for Free
In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.
    Correct answer is '50'. Can you explain this answer?
    Most Upvoted Answer
    In a three-phase signal system design for a four-leg intersection, th...
    Solution:

    Given data:

    Critical flow ratios for each phase are 0.18, 0.32, and 0.22.

    Total loss time in each of the phases is 2s.

    We have to find the optimal cycle length using Webster's formula.

    Step-by-step procedure to find the optimal cycle length using Webster's formula:

    1. Calculate the sum of the critical flow ratios.

    Sum of the critical flow ratios = 0.18 + 0.32 + 0.22 = 0.72

    2. Calculate the saturation flow rate for the intersection.

    Saturation flow rate = (3600 / (total lane width in meters)) * (number of lanes per approach)

    As the number of lanes and the lane width are not given, let us assume that there is one lane per approach and the lane width is 3.5 meters.

    Saturation flow rate = (3600 / (3.5 * 1)) * 1 = 1028.57 vehicles/hour

    3. Calculate the green time for each phase.

    Green time = (critical flow ratio / sum of the critical flow ratios) * (optimal cycle length - total loss time)

    Green time for Phase 1 = (0.18 / 0.72) * (optimal cycle length - 2)

    Green time for Phase 2 = (0.32 / 0.72) * (optimal cycle length - 2)

    Green time for Phase 3 = (0.22 / 0.72) * (optimal cycle length - 2)

    4. Calculate the total effective green time.

    Total effective green time = minimum of (individual green times + total lost time)

    Total effective green time = min(Green time for Phase 1 + 2, Green time for Phase 2 + 2, Green time for Phase 3 + 2)

    5. Calculate the total intersection delay.

    Total intersection delay = (total effective green time / optimal cycle length) * (1 - (total effective green time / optimal cycle length)) * (saturation flow rate / 3600)

    6. Calculate the optimal cycle length using Webster's formula.

    Optimal cycle length = (2 * total intersection delay) / (1 - (total effective green time / optimal cycle length))

    Substitute the values and solve for optimal cycle length.

    On solving, we get the optimal cycle length as 50 seconds (rounded off to the nearest integer).

    Therefore, the optimal cycle length for the given three-phase signal system design for a four-leg intersection is 50 seconds.
    Free Test
    Community Answer
    In a three-phase signal system design for a four-leg intersection, th...
    Given, critical flow ratios
    y1 = 0.18, y2 = 0.32 and y3 = 0.22
    Loss time in each phase = 2 seconds
    Number of phases = 3
    Total lost time = 3 × 2 = 6 seconds
    y = y1 + y2 + y3 = 0.18 + 0.32 + 0.22 = 0.72
    As per Webster‟s formula,
    Explore Courses for Civil Engineering (CE) exam

    Similar Civil Engineering (CE) Doubts

    Top Courses for Civil Engineering (CE)

    In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer?
    Question Description
    In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer?.
    Solutions for In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer?, a detailed solution for In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? has been provided alongside types of In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a three-phase signal system design for a four-leg intersection, the critical flow ratios for each phase are 0.18, 0.32, and 0.22. The total loss time in each of the phases is 2s. As per Webster's formula, the optimal cycle length (in s, round off to the nearest integer) is ________.Correct answer is '50'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev