A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)
    Correct answer is '3'. Can you explain this answer?
    Most Upvoted Answer
    A new facility has to be designed to do all the welding for 3 product...
    Attention Mechanical Engineering Students!
    To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
    Explore Courses for Mechanical Engineering exam

    Similar Mechanical Engineering Doubts

    Top Courses for Mechanical Engineering

    A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer?
    Question Description
    A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer?.
    Solutions for A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer?, a detailed solution for A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? has been provided alongside types of A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A new facility has to be designed to do all the welding for 3 products: A, B and C. Per unit welding time for each product is 20 s, 40 s and 50 s respectively. Daily demand forecast for product A is 450, for B is 360 and for C is 240. A welding line can operate efficiently for 220 minutes a day. Number of welding lines required is(Answer to the nearest integer)Correct answer is '3'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev