Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >   A small project has 12 activities - N, P, Q,... Start Learning for Free
A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.
The total float of the activity 'V' (in weeks, in integer) is ___________________.
    Correct answer is '0'. Can you explain this answer?
    Most Upvoted Answer
    A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y a...
    The critical path is:
    N - P - R - U - V - X - Z
    The total float on activity which is in critical path is zero.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer?
    Question Description
    A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer?.
    Solutions for A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer?, a detailed solution for A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? has been provided alongside types of A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the table.The total float of the activity 'V' (in weeks, in integer) is ___________________.Correct answer is '0'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev