The project activities are given in the following table along with the duration and dependency.

Which one of the following combinations is correct?
  • a)
    Total duration of the project = 22 days, Critical path is Q → S
  • b)
    Total duration of the project = 20 days, Critical path is Q → T
  • c)
    Total duration of the project = 22 days, Critical path is P → T
  • d)
    Total duration of the project = 20 days, Critical path is P → R
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
The project activities are given in the following table along with the...

Critical path = Q-S and Q-T also (max. time taken along the path) = 22 days
View all questions of this test
Most Upvoted Answer
The project activities are given in the following table along with the...

Critical path = Q-S and Q-T also (max. time taken along the path) = 22 days
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer?
Question Description
The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The project activities are given in the following table along with the duration and dependency.Which one of the following combinations is correct?a)Total duration of the project = 22 days, Critical path is Q → Sb)Total duration of the project = 20 days, Critical path is Q → Tc)Total duration of the project = 22 days, Critical path is P → Td)Total duration of the project = 20 days, Critical path is P → RCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev