Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy are
  • a)
    0
  • b)
    2
  • c)
    3
  • d)
    4
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Five jobs are scheduled on SPT rules are ABCDE which have processing ...
In case of finding number of jobs delivered late , find job loading sequence using EDD rule , jobs are loaded in the increasing order of these due dates.
Free Test
Community Answer
Five jobs are scheduled on SPT rules are ABCDE which have processing ...
Job Scheduling Problem with SPT Rules

In this problem, we have five jobs scheduled based on the Shortest Processing Time (SPT) rule. The jobs are labeled as A, B, C, D, and E, and their respective processing times are 4, 17, 14, 9, and 11 days. The due dates for these jobs are 6, 20, 18, 12, and 12 days from now, respectively.

Understanding SPT Rule

The SPT rule is a scheduling algorithm that prioritizes jobs based on their processing times. In this rule, jobs with shorter processing times are given higher priority and scheduled first.

Calculating Job Completion Times

To determine if a job is delivered tardy, we need to calculate the job completion times. The job completion time is the sum of the processing time and the waiting time for each job.

The job completion times for the given jobs are as follows:

Job A: Processing Time = 4 days, Completion Time = 4 days (no waiting time)
Job B: Processing Time = 17 days, Completion Time = 4 + 17 = 21 days
Job C: Processing Time = 14 days, Completion Time = 21 + 14 = 35 days
Job D: Processing Time = 9 days, Completion Time = 35 + 9 = 44 days
Job E: Processing Time = 11 days, Completion Time = 44 + 11 = 55 days

Determining Tardy Jobs

To determine if a job is delivered tardy, we compare its completion time with its due date. If the completion time is greater than the due date, the job is considered tardy.

The due dates for the given jobs are as follows:

Job A: Due Date = 6 days
Job B: Due Date = 20 days
Job C: Due Date = 18 days
Job D: Due Date = 12 days
Job E: Due Date = 12 days

Comparing the completion times with the due dates, we find that the following jobs are delivered tardy:

Job B: Completion Time = 21 days > Due Date = 20 days
Job C: Completion Time = 35 days > Due Date = 18 days
Job D: Completion Time = 44 days > Due Date = 12 days
Job E: Completion Time = 55 days > Due Date = 12 days

Therefore, four jobs (B, C, D, and E) out of the five scheduled jobs are delivered tardy.

Conclusion

Based on the SPT rule and the given processing times and due dates, four out of the five jobs (B, C, D, and E) are delivered tardy. Therefore, the correct answer is option D.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer?
Question Description
Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer?.
Solutions for Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Five jobs are scheduled on SPT rules are ABCDE which have processing times 4, 17, 14, 9,11 days respectively and their due dates are 6, 20, 18,12,12 days from now respectively.The number of jobs delivered tardy area)0b)2c)3d)4Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev