The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.
    Correct answer is '4000'. Can you explain this answer?
    Most Upvoted Answer
    The two-bin approach is used to control inventory for a particular lo...
    Q = 1000 units
    Total variable cost = A/Q x S+ Q/2 x CI
    = 40000/1000 X 50 + 1000/2 x 4
    = 2000 + 2000 = 4000
    When items in one bin are completely exhausted an order is placed. By the time the order materializes items in second bin are used and the process is repeated.
    Attention Mechanical Engineering Students!
    To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
    Explore Courses for Mechanical Engineering exam

    Similar Mechanical Engineering Doubts

    Top Courses for Mechanical Engineering

    The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer?
    Question Description
    The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer?.
    Solutions for The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer?, a detailed solution for The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? has been provided alongside types of The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The two-bin approach is used to control inventory for a particular low cost component. Each bin holds 1000 units. The annual usage of the component is 40000 units. Cost to order the component is around ₹ 50. If the actual annual holding cost per unit is only ₹ 4. The total variable cost (in ₹) for the two-bin approach is ________.Correct answer is '4000'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev