The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).
    Correct answer is '14'. Can you explain this answer?
    Most Upvoted Answer
    The demand of a certain part is 1000 parts/year and its cost is Rs. 10...
    Given data:
    Demand = 1000 parts/year
    Cost per part = Rs. 1000/part
    Ordering cost = Rs. 100/order
    Lead time = 5 days
    Holding cost = Rs. 20/part/year

    To find the inventory level for placing the orders, we need to calculate the Economic Order Quantity (EOQ) using the given data.

    Calculating EOQ:
    The EOQ formula is given by:
    EOQ = √((2 * Demand * Ordering cost) / Holding cost)

    Substituting the given values:
    EOQ = √((2 * 1000 * 100) / 20)
    EOQ = √(2000000 / 20)
    EOQ = √100000
    EOQ = 316.22 (approx.)

    Since we need to round off the answer to the nearest integer, the EOQ is 316.

    Calculating the inventory level:
    The inventory level is the quantity of parts that should be available in stock when an order is placed. It is calculated by adding the demand during lead time to the EOQ.

    Inventory level = Demand during lead time + EOQ

    Demand during lead time = Demand * (Lead time / 365)
    Demand during lead time = 1000 * (5 / 365)
    Demand during lead time = 13.70 (approx.)

    Inventory level = 13.70 + 316
    Inventory level = 329.70 (approx.)

    Rounding off the inventory level to the nearest integer, we get 330.

    Therefore, the inventory level for placing the orders is 330 parts (rounded off to the nearest integer).

    However, the correct answer is given as 14, which seems to be a mistake. The calculated inventory level should be 330, not 14.
    Free Test
    Community Answer
    The demand of a certain part is 1000 parts/year and its cost is Rs. 10...
    Given :
    Demand of certain part (D) = 1000 parts/year
    Cost (C) = Rs . 1000/part
    Ordering cost (C0) = Rs. 100 / order
    Lead time (LT) 5 days T
    Holding cost (Ch) Rs. 20/part/year

    Where, R.O.L = Re-order level 
    ∵ R.O.L = LT x d   … (i)
    Where, d = consumption per day 

    From equation (i), 

    R.O.L = 13.69 14 parts Hence, the inventory level for placing the orders is 14 parts.
    Attention Mechanical Engineering Students!
    To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer?
    Question Description
    The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer?.
    Solutions for The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer?, a detailed solution for The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? has been provided alongside types of The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _________ parts (round off to the nearest integer).Correct answer is '14'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev