The discharge per unit draw down at the well is known as :-
  • a)
    Specific yield
  • b)
    Specific storage
  • c)
    Specific retention
  • d)
    Specific capacity
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
The discharge per unit draw down at the well is known as :-a)Specific ...
The discharge per unit drawdown at the well is known as specific capacity.

Explanation:
The specific capacity of a well is a measure of its productivity and efficiency. It is defined as the discharge of water per unit of drawdown at the well. In other words, it represents the amount of water a well can produce relative to the amount of drawdown, or lowering of the water level, in the well.

Significance of specific capacity:
The specific capacity of a well is an important parameter in groundwater studies and well design. It provides valuable information about the aquifer properties and the performance of the well. By analyzing the specific capacity, engineers and hydrogeologists can assess the sustainability and potential yield of a well.

Factors affecting specific capacity:
Several factors influence the specific capacity of a well, including:
- Aquifer properties: The permeability and storage characteristics of the aquifer influence the flow of water into the well and, therefore, its specific capacity.
- Well design: The diameter, depth, and screen length of the well, as well as the presence of gravel packs or other filtering materials, can affect the specific capacity.
- Pumping rate: The rate at which water is pumped from the well can impact the drawdown and, consequently, the specific capacity.
- Aquifer recharge: The rate at which the aquifer is recharged by natural processes, such as rainfall or inflow from adjacent aquifers, can also affect the specific capacity.

Measurement of specific capacity:
To determine the specific capacity of a well, a pumping test is typically conducted. During the test, the well is pumped at a constant rate, and the resulting drawdown in the water level is measured. The discharge of water from the well is also measured. By dividing the discharge by the drawdown, the specific capacity can be calculated.

Conclusion:
The specific capacity of a well is an important parameter in assessing its performance and productivity. It is a measure of the discharge of water per unit of drawdown at the well. By analyzing the specific capacity, engineers and hydrogeologists can make informed decisions regarding well design and aquifer management.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer?
Question Description
The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer?.
Solutions for The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The discharge per unit draw down at the well is known as :-a)Specific yieldb)Specific storagec)Specific retentiond)Specific capacityCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev