Banking Exams Exam  >  Banking Exams Questions  >   x men can complete a work in 6 days and 6x/5... Start Learning for Free
x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the work
  • a)
    60 days
  • b)
    96 days
  • c)
    48 days
  • d)
    72 days
  • e)
    None of these
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
x men can complete a work in 6 days and 6x/5 women can complete the s...
To solve this question, let's assume that one man's work efficiency is M units per day, one woman's work efficiency is W units per day, and one child's work efficiency is C units per day.

Given Information:
- X men can complete the work in 6 days, so their total work efficiency is 6M units per day.
- 6x/5 women can complete the work in 8 days, so their total work efficiency is (8/6x/5)W units per day.
- 3x/5 children can complete the work in 8 days, so their total work efficiency is (8/3x/5)C units per day.
- 15 men, 16 women, and 4 children can complete the work in 2 days, so their total work efficiency is (2/15M + 2/16W + 2/4C) units per day.

Now, we can set up the equation using the given information:

6M = (8/6x/5)W = (8/3x/5)C = (2/15M + 2/16W + 2/4C)

Simplifying the equation:
- Multiply both sides by 15 to eliminate the fraction: 90M = 20W + 30C
- Multiply both sides by 16 to eliminate the fraction: 96M = 20W + 48C

Now, we have two equations:
90M = 20W + 30C
96M = 20W + 48C

Solving these equations simultaneously, we can find the values of M, W, and C.

Subtracting the first equation from the second equation:
96M - 90M = 48C - 30C
6M = 18C
M = 3C

Substituting the value of M in the first equation:
90(3C) = 20W + 30C
270C = 20W + 30C
240C = 20W
12C = W

Now, we know that M = 3C and W = 12C.

Substituting these values in the first equation:
90(3C) = 20(12C) + 30C
270C = 240C + 30C
270C = 270C

Therefore, the values of M, W, and C are consistent and valid.

Finding the time taken by one man to complete the work:
We know that one man's work efficiency is M units per day.
Since M = 3C, we can say that one man's work efficiency is 3 times the work efficiency of one child.
Therefore, the time taken by one man to complete the work is 3 times the time taken by one child to complete the work.

Given that the work is completed by 4 children in 8 days, the time taken by one child to complete the work is 4 * 8 = 32 days.

Therefore, the time taken by one man to complete the work is 3 * 32 = 96 days.

Hence, the correct answer is option 'A' - 60 days.
Free Test
Community Answer
x men can complete a work in 6 days and 6x/5 women can complete the s...
Time taken by one man to complete the work = 6x
Time taken by one woman to complete the work = 6x/5 * 8 = 48x/5
Time taken by one child to complete the work = 3x/5 * 8 = 24x/5
15/6x + 16/(48x/5) + 4/(24x/5) = 1/2
5/2x + (16 * 5)/48x + (4 * 5)/24x = 1/2
5/2x + 5/3x + 5/6x = 1/2
(15 + 10 + 5)/6x = 1/2
30/6x = 1/2
x = 10
Time taken by one man to complete the work = 6 * 10 = 60 days
Explore Courses for Banking Exams exam

Similar Banking Exams Doubts

x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?
Question Description
x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?.
Solutions for x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice x men can complete a work in 6 days and 6x/5 women can complete the same work in 8 days and 3x/5 children can complete the same work in 8 days. 15 men, 16 women and 4 children together can complete the work in 2 days. Find the time taken by one man to complete the worka)60 daysb)96 daysc)48 daysd)72 dayse)None of theseCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev