Question Description
It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer?.
Solutions for It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer?, a detailed solution for It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice It was expected that 10 men together would complete a piece of work in 40 days. But after a few days, they increased their efficiency by 25% and completed the work six days earlier. How many days after the start of the work did they increase their efficiency?a)5b)6c)8d)10e)12Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.