Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____
  • a)
    vertical lead and lift
  • b)
    normal lead and lift
  • c)
    horizontal lead and lift
  • d)
    transverse lead and lift
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Normally earthwork is estimated for 30 m lead for distance and 1.5 m l...
The Answer:
The correct answer is option 'B' - normal lead and lift.

Explanation:
In earthwork estimation, the terms 'lead' and 'lift' are used to specify the distance and height or depth, respectively. The lead refers to the horizontal distance over which the earth is to be transported, while the lift refers to the vertical height or depth of excavation or filling.

Normal Lead and Lift:
The term 'normal' in this context refers to the standard or typical value used in earthwork estimation. In general, earthwork is estimated for a lead of 30 meters and a lift of 1.5 meters. These values are considered as the standard or normal lead and lift for earthwork calculations.

Significance of Normal Lead and Lift:
The normal lead and lift values are used as a reference in earthwork estimation to provide a consistent basis for calculating the quantities of earth to be excavated or filled. By using these standard values, engineers and estimators can ensure uniformity and accuracy in their calculations, making it easier to compare and analyze different projects.

Alternative Leads and Lifts:
While the normal lead and lift are commonly used, it is important to note that these values can vary depending on the specific project requirements. Certain projects may involve longer or shorter leads, depending on the distance over which the earth needs to be transported. Similarly, the lift can vary based on the depth of excavation or filling required for a particular project.

Conclusion:
In earthwork estimation, the terms 'lead' and 'lift' are used to define the distance and height or depth, respectively. The normal lead and lift values of 30 meters and 1.5 meters provide a consistent basis for estimating earthwork quantities. However, it is essential to consider project-specific requirements and adjust the lead and lift values accordingly for accurate calculations.
Free Test
Community Answer
Normally earthwork is estimated for 30 m lead for distance and 1.5 m l...
Normal rate for earthwork is for 30 m lead and 1.5 m lift. For greater lead or lift the rates will be different (higher) for every unit of 30 m lead and for every unit of 1.5 m lift. The earthwork is, therefore, estimated separately for every 30 m lead and for every 1.5 m lift.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer?
Question Description
Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Normally earthwork is estimated for 30 m lead for distance and 1.5 m lift for height or depth, and this distance of 30 m and the height of 1.5 m are known as ____a)vertical lead and liftb)normal lead and liftc)horizontal lead and liftd)transverse lead and liftCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev