Which one of the following is the base for resource levelling?
  • a)
    Delaying the completion of critical activities
  • b)
    Delaying the start of noncritical activities
  • c)
    Reducing completion time of critical activities
  • d)
    Not delaying the completion of critical activities
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Which one of the following is the base for resource levelling?a)Delayi...
Resource Levelling

Resource levelling is a scheduling technique used to optimize the use of resources in a project. It involves adjusting the start and finish dates of activities to ensure that the resource requirements are met within the available resources.

Base for Resource Levelling

The base for resource levelling is the decision-making criteria used to adjust the schedule. The options for the base of resource levelling are:

a) Delaying the completion of critical activities
b) Delaying the start of non-critical activities
c) Reducing the completion time of critical activities
d) Not delaying the completion of critical activities

The correct answer is option B, i.e., delaying the start of non-critical activities.

Explanation

Delaying the start of non-critical activities is the most appropriate base for resource levelling because it allows for the optimization of resources without affecting the critical path. Non-critical activities are those that can be delayed without affecting the project's completion date. By delaying their start, the resources required for these activities can be utilized for critical activities, which cannot be delayed without affecting the project's completion date.

Delaying the completion of critical activities or reducing the completion time of critical activities is not a viable base for resource levelling because it would affect the project's critical path and delay the project's completion date. Not delaying the completion of critical activities is also not a viable base because it does not allow for the optimization of resources.

Conclusion

In conclusion, delaying the start of non-critical activities is the most appropriate base for resource levelling because it allows for the optimization of resources without affecting the critical path or delaying the project's completion date.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer?
Question Description
Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following is the base for resource levelling?a)Delaying the completion of critical activitiesb)Delaying the start of noncritical activitiesc)Reducing completion time of critical activitiesd)Not delaying the completion of critical activitiesCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev