Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Updating may result ina)change of critical pa... Start Learning for Free
Updating may result in
  • a)
    change of critical path
  • b)
    decrease of project completion time
  • c)
    increase of project completion time
  • d)
    all of the above
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Updating may result ina)change of critical pathb)decrease of project c...
Updating may result in all of the above

Changes in a project can affect its critical path and completion time. Here are some reasons why updating a project may result in any or all of the above:

Change in scope: When the scope of a project changes, it may result in additional tasks that were not included in the initial plan. As a result, the critical path may change, and the project completion time may increase.

Resource availability: If there are changes in the availability of resources, such as labor, materials, or equipment, the critical path may change. If there is a shortage of resources, it may result in a delay in the project completion time.

Dependencies: In some cases, a project may have dependencies on other projects or tasks. If there are any changes in these dependencies, it may affect the critical path and the project completion time.

Risk factors: Risk factors such as environmental conditions, safety concerns, etc. may arise during a project. If these risks are not managed effectively, they can cause delays in the project completion time.

Conclusion:

Updating a project can have significant impacts on its critical path and completion time. It is essential to manage changes effectively to minimize any negative effects on the project's timeline. By keeping track of changes and managing risks, project managers can ensure that their projects stay on track and are completed on time.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Question Description
Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer?.
Solutions for Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Updating may result ina)change of critical pathb)decrease of project completion timec)increase of project completion timed)all of the aboveCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev