The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time?
Most Upvoted Answer
The time which results in the least possible direct cost of an activit...
Explanation:

The time which results in the least possible direct cost of an activity is called the optimum time. It is also known as the most efficient time to complete an activity. To calculate the optimum time, we need to consider three different times: normal time, crash time, and slow time.

Normal Time:
Normal time is the time needed to complete an activity under normal working conditions. This time is estimated based on the average performance of the workers and the availability of resources. It is the time taken to complete an activity without any additional resources or working hours.

Crash Time:
Crash time is the shortest possible time to complete an activity by using additional resources or working hours. This time is achieved by increasing the workforce, using more efficient equipment, or working overtime. The crash time is always shorter than the normal time.

Slow Time:
Slow time is the longest possible time to complete an activity by using fewer resources or working hours. This time is achieved by decreasing the workforce, using less efficient equipment, or working fewer hours. The slow time is always longer than the normal time.

Optimum Time:
The optimum time is the time that results in the least possible direct cost of an activity. It is the most efficient time to complete an activity, which balances the cost and the time required to complete the activity. The optimum time is calculated by considering the normal time, crash time, and slow time, and selecting the time that provides the best balance between cost and time.

In conclusion, the optimum time is the time that results in the least possible direct cost of an activity. It is achieved by balancing the cost and the time required to complete an activity. The optimum time is calculated by considering the normal time, crash time, and slow time, and selecting the time that provides the best balance between cost and time.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time?
Question Description
The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? for Computer Science Engineering (CSE) 2024 is part of Computer Science Engineering (CSE) preparation. The Question and answers have been prepared according to the Computer Science Engineering (CSE) exam syllabus. Information about The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? covers all topics & solutions for Computer Science Engineering (CSE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time?.
Solutions for The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? in English & in Hindi are available as part of our courses for Computer Science Engineering (CSE). Download more important topics, notes, lectures and mock test series for Computer Science Engineering (CSE) Exam by signing up for free.
Here you can find the meaning of The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? defined & explained in the simplest way possible. Besides giving the explanation of The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time?, a detailed solution for The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? has been provided alongside types of The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? theory, EduRev gives you an ample number of questions to practice The time which results in the least possible direct cost of an activity is called Ops: A. Onormal time B. slow time C. O crash time D. O standared time? tests, examples and also practice Computer Science Engineering (CSE) tests.
Explore Courses for Computer Science Engineering (CSE) exam

Top Courses for Computer Science Engineering (CSE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev