A master production schedule specifies
  • a)
    the financial resources required for production
  • b)
    what component is to be made, and when
  • c)
    what product is to be made, and when
  • d)
    the labor hours required for production
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
A master production schedule specifiesa)the financial resources requir...
C) What product is to be made, and when

The master production schedule (MPS) is an important tool used in production planning and control. It is a detailed plan that specifies the quantity and timing of the products to be manufactured, based on the demand forecast and available resources. The correct answer to this question is option C, which states that the master production schedule specifies what product is to be made, and when.

1. Purpose of the Master Production Schedule:
The primary purpose of the master production schedule is to ensure that the production process is aligned with the demand for the final product. It helps in maintaining a balance between customer demand and production capacity.

2. Product Identification:
The MPS identifies the specific products that are to be manufactured. It includes information such as the product code, description, and other relevant details.

3. Timeframe:
The master production schedule also specifies the time period during which the production is planned. It provides a detailed timeline for each product, indicating when it should be started and completed.

4. Production Quantities:
Another crucial aspect of the MPS is the determination of production quantities. It specifies the number of units to be manufactured for each product during a specific time period. This information is based on the demand forecast, taking into consideration factors such as customer orders, inventory levels, and market trends.

5. Resource Planning:
While the MPS primarily focuses on the product and timing aspects, it indirectly influences resource planning. By providing information on the products to be manufactured and their quantities, it helps in estimating the required resources such as raw materials, labor, and equipment. However, the MPS does not directly specify financial resources or labor hours required for production, as mentioned in options A and D.

In conclusion, the correct answer to the question is option C. The master production schedule specifies what product is to be made, and when, ensuring that production is aligned with customer demand and available resources.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer?
Question Description
A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer?.
Solutions for A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A master production schedule specifiesa)the financial resources required for productionb)what component is to be made, and whenc)what product is to be made, and whend)the labor hours required for productionCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev