Which one of the following is NOT a decision taken during the aggregate production planning stage?
[2012]
  • a)
    Scheduling of machines
  • b)
    Amount of labour to be committed
  • c)
    Rate at which production should happen
  • d)
    Inventory to be carried forward
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
Which one of the following is NOT a decision taken during the aggregat...
Explanation:
The aggregate production planning stage is a crucial step in the production planning process, where decisions are made regarding the overall production strategy for a specified period of time. This stage focuses on determining the optimal production rate, workforce levels, and inventory levels to meet the demand forecasted for the planning horizon.

Decision 1: Scheduling of Machines
During the aggregate production planning stage, one of the key decisions is the scheduling of machines. This involves determining the sequence and timing of production activities to optimize machine utilization and minimize downtime. The goal is to ensure that machines are used efficiently and effectively to meet the production targets.

Decision 2: Amount of Labor to be Committed
Another important decision made during the aggregate production planning stage is the determination of the amount of labor to be committed. This decision involves estimating the required workforce levels to meet the production targets. Factors such as labor productivity, overtime, and subcontracting may be considered to ensure that the labor requirements are met.

Decision 3: Rate at Which Production Should Happen
The rate at which production should happen is a critical decision made during the aggregate production planning stage. This decision involves determining the production rate required to meet the forecasted demand. It takes into account factors such as the desired level of customer service, capacity constraints, and inventory levels. The objective is to balance production levels to meet customer demand while minimizing costs and maintaining a reasonable level of inventory.

Decision 4: Inventory to be Carried Forward
The decision regarding the inventory to be carried forward is also made during the aggregate production planning stage. This decision involves determining the optimal level of inventory to be maintained at the end of each planning period. Factors such as carrying costs, stockouts, and lead times are considered to ensure that the inventory levels are sufficient to meet customer demand without incurring excessive costs.

Conclusion:
Among the options provided, the decision that is NOT taken during the aggregate production planning stage is the "Amount of labor to be committed" (Option B). While labor requirements are considered and estimated during this stage, the specific decision regarding the amount of labor to be committed is typically made during the detailed production planning stage, where specific work schedules and assignments are determined.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer?
Question Description
Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which one of the following is NOT a decision taken during the aggregate production planning stage?[2012]a)Scheduling of machinesb)Amount of labour to be committedc)Rate at which production should happend)Inventory to be carried forwardCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev