Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The PERT calculations yield a project length ... Start Learning for Free
The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain?
Most Upvoted Answer
The PERT calculations yield a project length of 50 weeks, with a varia...
Calculating the Completion Time of a Project with PERT

Given:
- Project length: 50 weeks
- Variance: 9
- Probability factor Z: 1.65 for 95% probability

Calculating the Expected Completion Time:
To calculate the expected completion time of the project, we can use the formula:

Expected Completion Time = Project Length + (Probability Factor Z * Square Root of Variance)

Let's plug in the given values into the formula:

Expected Completion Time = 50 + (1.65 * √9)
Expected Completion Time = 50 + (1.65 * 3)
Expected Completion Time = 50 + 4.95
Expected Completion Time = 54.95 weeks

Therefore, the expected completion time of the project with a 95% probability is 54.95 weeks.

Explanation:
The PERT (Program Evaluation and Review Technique) is a project management tool that helps in estimating the time required to complete a project. It takes into account three time estimates for each activity: optimistic time (O), pessimistic time (P), and most likely time (M). From these estimates, the expected time (TE) and variance (V) can be calculated using the following formulas:

TE = (O + 4M + P) / 6
V = ((P - O) / 6)²

Once the expected time and variance for each activity are determined, the project's expected completion time can be calculated by summing up the expected times of all activities. The project's variance can be calculated by summing up the variances of all activities.

In this case, we are given the project length (50 weeks) and variance (9). The variance represents the measure of uncertainty or risk associated with the project. A higher variance indicates a greater degree of uncertainty.

To calculate the expected completion time with a specific probability, we can use the probability factor Z. The Z value represents the number of standard deviations from the mean in a standard normal distribution. For example, a Z value of 1.65 corresponds to a 95% probability.

By multiplying the probability factor Z with the square root of the variance and adding it to the project length, we can estimate the expected completion time with a given probability. In this case, the expected completion time with a 95% probability is calculated to be 54.95 weeks.

Conclusion:
The PERT calculations provide an estimate of the expected completion time of a project, taking into account the uncertainty or risk associated with the project. By using the probability factor Z, we can calculate the expected completion time with a specific probability. In this case, the project is expected to be completed within 54.95 weeks with a 95% probability.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain?
Question Description
The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain?.
Solutions for The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? defined & explained in the simplest way possible. Besides giving the explanation of The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain?, a detailed solution for The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? has been provided alongside types of The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? theory, EduRev gives you an ample number of questions to practice The PERT calculations yield a project length of 50 weeks, with a variance of 9. Within how many weeks would you expect the project to be completed with probability of 95%, take probability factor Z equal to 1.65 for 95% probability: (Ans is 54.95). Can anyone explain? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev