For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the project in 63 weeks will be________%, using the below table.
    Correct answer is '99-99.02'. Can you explain this answer?
    Verified Answer
    For a construction project, PERT calculation yield a project duration ...
    Concept:
    Probability factor
    Where
    TS = Scheduled time required to complete the project
    TE = expected completion time of the project
    σ = standard deviation
    Calculation:
    Expected completion time of the project, TE = 50 weeks
    variance = 25 weeks
    Scheduled Completion time of project = 63weeks
    ∴  standard deviation
    Probability factor
    z = 2.6
    Probability = 97.72 + (2.6 - 2) 
    Probability = 99.01%
    View all questions of this test
    Explore Courses for Civil Engineering (CE) exam

    Similar Civil Engineering (CE) Doubts

    Top Courses for Civil Engineering (CE)

    For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer?
    Question Description
    For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer?.
    Solutions for For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer?, a detailed solution for For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? has been provided alongside types of For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice For a construction project, PERT calculation yield a project duration of 50 weeks with a variance of 25 weeks. The probability of completion of the projectin 63 weeks will be________%, using the below table.Correct answer is '99-99.02'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev