Question Description
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared
according to
the Civil Engineering (CE) exam syllabus. Information about For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer?.
Solutions for For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE).
Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer?, a detailed solution for For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? has been provided alongside types of For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice For a construction project. The mean and standard deviation of the completion time are 200 days and 6.1 days, respectively. Assume normal distribution and use the value of standard normal deviate Z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be __________Correct answer is '210'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.