Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  In PERT analysis, the probability of completi... Start Learning for Free
In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)
  • a)
    0%
  • b)
    100%
  • c)
    Less than 100%
  • d)
    50%
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
In PERT analysis, the probability of completion of the project in 40 d...
The correct answer is option D: 50%. Let's understand why.

1. PERT Analysis:
PERT (Program Evaluation and Review Technique) is a project management tool used to analyze and estimate the time required to complete a project. It uses three time estimates for each activity: the optimistic time (TO), the most likely time (TM), and the pessimistic time (TP).

2. Expected Time (TE):
The expected time (TE) for each activity is calculated using the formula:
TE = (TO + 4TM + TP) / 6

3. Critical Path:
In PERT analysis, the critical path is the longest path of activities that determines the minimum time required to complete the project. It consists of activities with zero slack or float time, meaning any delay in these activities will delay the entire project.

4. Probability of Completion:
To calculate the probability of completing the project within a certain time, we need to consider the critical path and the sum of the expected times for all the activities on that path.

In this case, the earliest expected time (TE) of the last event is given as 40 days. This means that the sum of the expected times for all the activities on the critical path is 40 days.

5. Probability Calculation:
To calculate the probability of completing the project in 40 days or less, we need to consider the distribution of the critical path.

Since PERT uses a beta distribution, the expected time (TE) represents the mean of the distribution. In a symmetrical beta distribution, the standard deviation (SD) is calculated as:
SD = (TP - TO) / 6

Using this information, we can calculate the Z-score (standard score) for the desired completion time. The Z-score represents the number of standard deviations the desired completion time is away from the mean.

Z-score = (Desired Completion Time - TE) / SD

6. Z-score Calculation:
In this case, the desired completion time is 40 days and the TE is also 40 days. Since the SD is positive (assuming TP is greater than TO), the Z-score will be zero.

Z-score = (40 - 40) / SD = 0

7. Probability Calculation:
The probability of completing the project in 40 days or less can be calculated using the Z-table or a statistical calculator. A Z-score of zero corresponds to a probability of 50%.

Therefore, the probability of completion of the project in 40 days is 50%.
Free Test
Community Answer
In PERT analysis, the probability of completion of the project in 40 d...
Given:
Scheduled completion time of the project (TS) = 40 days
Expected completion time of the project (TE) = 40 days


The probability factor (Z) is zero then the probability that the project will be completed in 40 days is 50%.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer?
Question Description
In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer?.
Solutions for In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer?, a detailed solution for In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)a)0%b)100%c)Less than 100%d)50%Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev