The reduction in project time normally results in
  • a)
    decreasing the direct cost and indirect cost
  • b)
    increasing the direct cost and decreasing the indirect cost
  • c)
    increasing the direct cost and indirect cost both
  • d)
    decreasing the direct cost and increasing indirect cost
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
The reduction in project time normally results ina)decreasing the dire...
In the case of CPM analysis, the total project cost is the sum of indirect cost and direct cost. 
Indirect cost:
  • The indirect cost of a project includes overhead cost, losses, penality, rentals, project accommodations.
  • The indirect cost is directly proportional to project duration with a linear variation. So if time is reduced then cost is also reduced.
Direct cost:
  • Direct cost is the cost that is directly dependent on the number of resources involved for the completion of activities. It includes labor, materials, plants, and machining.
  • To get the same work done in less time, we have to increase the amount of labor, equipment, and time-saving material that too at extra charges which simply means an increased direct cost. 
Free Test
Community Answer
The reduction in project time normally results ina)decreasing the dire...
Reduction in project time results in increasing the direct cost and decreasing the indirect cost.

Explanation:


Direct costs are those costs that can be directly attributed to the production of goods or services. In the context of a project, direct costs are the costs directly associated with the execution of the project, such as labor, materials, equipment, and subcontractors.

Indirect costs, on the other hand, are costs that cannot be directly attributed to a specific project but are necessary for the overall operation of the organization. Indirect costs can include administrative expenses, overhead costs, and general expenses.

When the project time is reduced, several factors come into play that affect the project costs. Here is a detailed explanation of how the reduction in project time impacts the direct and indirect costs:

1. Direct Costs:
- Increase in Labor Costs: When the project time is reduced, the labor force needs to work more intensively to meet the deadlines. This may require overtime work or additional labor resources, leading to an increase in labor costs.
- Increase in Material Costs: In order to complete the project within a shorter timeframe, there may be a need for expedited delivery of materials or the use of more expensive materials to speed up the construction process. This can result in an increase in material costs.
- Increase in Equipment Costs: Similar to labor and material costs, the use of equipment may need to be intensified to meet the project schedule. This can result in additional equipment rental or maintenance costs, leading to an increase in direct costs.

2. Indirect Costs:
- Decrease in Administrative Expenses: With a reduction in project time, there is less time required for administrative tasks such as project management, documentation, and coordination. This can lead to a decrease in administrative expenses.
- Decrease in Overhead Costs: Overhead costs are those costs that are not directly attributable to a specific project but are necessary for the overall operation of the organization. When the project time is reduced, there is a decrease in the duration of overhead costs, resulting in a decrease in indirect costs.

Therefore, the reduction in project time generally leads to an increase in direct costs due to increased labor, material, and equipment expenses. On the other hand, indirect costs tend to decrease as administrative expenses and overhead costs are reduced. Hence, the correct answer is option 'B' - increasing the direct cost and decreasing the indirect cost.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer?
Question Description
The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer?.
Solutions for The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The reduction in project time normally results ina)decreasing the direct cost and indirect costb)increasing the direct cost and decreasing the indirect costc)increasing the direct cost and indirect cost bothd)decreasing the direct cost and increasing indirect costCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev