What percentage of the estimated cost, is considered as contingencies?
  • a)
    20% to 25%
  • b)
    10% to 15%
  • c)
    3% to 5%
  • d)
    1% to 2%
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
What percentage of the estimated cost, is considered as contingencies?...
Contingencies- these are incidental expenses of miscellaneous nature which cannot be classified under any distinct item sub-head in the preparation of estimate. Certain amount of 3% to 5% of estimated cost is added to the total estimate to account for contingencies.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer?
Question Description
What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer?.
Solutions for What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer?, a detailed solution for What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice What percentage of the estimated cost, is considered as contingencies?a)20% to 25%b)10% to 15%c)3% to 5%d)1% to 2%Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev