If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared
according to
the Civil Engineering (CE) exam syllabus. Information about If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer?.
Solutions for If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE).
Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer?, a detailed solution for If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice If the pessimistic estimate of a project is Rs. 12 Cr, the optimistic is Rs. 9 Cr and the most likely estimate is Rs. 10 Cr, then the expected value (Rs. in Cr) would bea)10.16b)10c)11.42d)12Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.