Which of the following is correct?
1) Prime cost refers to the actual cost of articles at shop and supply of articles only
2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have received
  • a)
    only 1
  • b)
    only 2
  • c)
    both
  • d)
    none of these
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Which of the following is correct?1) Prime cost refers to the actual c...
Prime cost- actual or purchase cost of any item at shop and refers to the supply of items but not to carrying out of work. For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have received.
There is no profit for this supply but the actual cost of carriage is allowed to the contractor, if specified.
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer?
Question Description
Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which of the following is correct?1) Prime cost refers to the actual cost of articles at shop and supply of articles only2) For payment to the contractor, actual price paid to merchants will be considered for prime cost articles ignoring any cash discounts the contractor may have receiveda)only 1b)only 2c)bothd)none of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev