A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
  • a)
    11 days
  • b)
    12 days
  • c)
    13 days
  • d)
    14 days
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
A, B and C can do a piece of work in 24 days, 30 days and 40 days resp...
One day's work of A, B and C = (1/24 + 1/30 + 1/40) = 1/10.
C leaves 4 days before completion of the work, which means only A and B work during the last 4 days.
Work done by A and B together in the last 4 days = 4 (1/24 + 1/30) = 3/10.
Remaining Work = 7/10, which was done by A,B and C in the initial number of days. 
Number of days required for this initial work = 7 days. 
Thus, the total numbers of days required = 4 + 7 = 11 days.
View all questions of this test
Most Upvoted Answer
A, B and C can do a piece of work in 24 days, 30 days and 40 days resp...
Understanding the problem:
A, B, and C can do a piece of work in 24 days, 30 days, and 40 days respectively. They started the work together but C left 4 days before the completion of the work. We need to find out in how many days the work was completed.

Solution:
Let's first find out the efficiency of each person per day:
- A's efficiency = 1/24
- B's efficiency = 1/30
- C's efficiency = 1/40

Working together:
When they work together, their combined efficiency per day = 1/24 + 1/30 + 1/40 = (5 + 4 + 3)/120 = 12/120 = 1/10
Let's assume the total work is 120 units (L.C.M of 24, 30, and 40).

Calculation:
- In the given time, A, B, and C together completed the work at the rate of 1/10 per day.
- Let the total number of days taken to complete the work be x.
- Therefore, the total work done by A, B, and C together in x days = 1/10 * x
- Work done by C in x-4 days = (x-4) * 1/40
Given that A, B, and C together completed the work in x days. Therefore,
1/24 * x + 1/30 * x + 1/40 * (x-4) = 1
Solving this equation, we get x = 11 days
Therefore, the work was completed in 11 days.
So, the correct answer is option 'a) 11 days'.
Explore Courses for UGC NET exam
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer?
Question Description
A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? for UGC NET 2025 is part of UGC NET preparation. The Question and answers have been prepared according to the UGC NET exam syllabus. Information about A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for UGC NET 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer?.
Solutions for A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for UGC NET. Download more important topics, notes, lectures and mock test series for UGC NET Exam by signing up for free.
Here you can find the meaning of A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?a)11 daysb)12 daysc)13 daysd)14 daysCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice UGC NET tests.
Explore Courses for UGC NET exam

Top Courses for UGC NET

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev