Which of the following factors are to be considered for production scheduling?
1. Sales forecast
2. Component design
3. Route sheet  
4. Time stand ards
Select the correct answer using the codes given below: 
  • a)
    1, 2 and 3  
  • b)
    1, 2 and 4        
  • c)
    1, 3 and 4
  • d)
    2, 3 and 4 
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
Which of the following factors are to be considered for production sch...
Factors to Consider for Production Scheduling

Production scheduling is an important aspect of manufacturing that helps in optimizing resources, reducing lead times, and improving productivity. The following factors are to be considered for production scheduling:

1. Sales Forecast
Sales forecast is an estimate of the future demand for a product or service. It is an important input for production scheduling as it helps in determining the quantity and timing of production. A company can use various methods to forecast sales, such as historical data analysis, market research, and trend analysis. By considering the sales forecast, a company can plan its production schedule to meet the demand and avoid overproduction or stockouts.

2. Component Design
Component design refers to the process of designing the parts or components that make up a product. The design of components can affect the production process, as some components may require specialized equipment or processes. By considering the component design, a company can plan its production schedule to ensure that the necessary resources and equipment are available to produce the components on time.

3. Route Sheet
A route sheet is a document that details the sequence of operations required to manufacture a product. It includes information such as the machines, tools, and materials required for each operation, as well as the time required to perform each operation. By considering the route sheet, a company can plan its production schedule to ensure that the necessary resources and equipment are available to perform each operation on time.

4. Time Standards
Time standards refer to the amount of time required to perform a specific operation or task. By considering time standards, a company can plan its production schedule to ensure that the necessary time is allocated for each operation. This can help in improving productivity, reducing lead times, and avoiding delays.

Conclusion
In conclusion, the factors to be considered for production scheduling include sales forecast, component design, route sheet, and time standards. By considering these factors, a company can plan its production schedule to meet the demand, optimize resources, and improve productivity.
Free Test
Community Answer
Which of the following factors are to be considered for production sch...
Production scheduling is carried after sales forecasting has already taken place. So, option of sales forecast is out an initio
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer?.
Solutions for Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Which of the following factors are to be considered for production scheduling?1. Sales forecast2. Component design3. Route sheet 4. Time stand ardsSelect the correct answer using the codes given below:a)1, 2 and 3 b)1, 2 and 4 c)1, 3 and 4d)2, 3 and 4Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev