In PERT analysis a critical activity has 
  • a)
    Maximum Float  
  • b)
    Zero Float  
  • c)
    Maximum Cost  
  • d)
    Minimum Cost
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c...
PERT Analysis and Critical Activity

PERT (Program Evaluation and Review Technique) analysis is a project management tool used to evaluate and analyze the tasks involved in completing a project. It helps to identify the critical path and critical activities that are essential for the successful completion of the project. The critical path includes all the activities that have zero float or slack, which means any delay in these activities will delay the entire project.

Critical Activity and Zero Float

A critical activity is an activity that has zero float or slack in the PERT analysis. It means that the activity has no room for delay or flexibility, and any delay in the critical activity will delay the whole project. The critical path includes all the critical activities, and the duration of the project is determined by the critical path.

Importance of Identifying Critical Activities

Identifying critical activities is essential for project managers as they need to focus their attention on these activities to ensure they are completed on time. Any delay in the critical activities will delay the entire project, and project managers need to take appropriate actions to avoid delays.

Example of a Critical Activity

Suppose a construction project has a critical activity of laying the foundation of a building. If this activity is delayed due to any reason, the entire project will be delayed, and the project completion date will be pushed back. Therefore, project managers need to focus on completing this activity on time to ensure the project is completed within the given timeframe.

Conclusion

In PERT analysis, a critical activity is an activity that has zero float or slack. Identifying critical activities is essential for project managers as they need to focus their attention on completing these activities on time to ensure the project is completed within the given timeframe.
Free Test
Community Answer
In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c...
B
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In PERT analysis a critical activity hasa)Maximum Float b)Zero Float c)Maximum Cost d)Minimum CostCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev