Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  A triangular DRH due to a storm has a time ba... Start Learning for Free
A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.
    Correct answer is '5'. Can you explain this answer?
    Verified Answer
    A triangular DRH due to a storm has a time base of 80 h and a peak flo...
    (Area under DRH) = (Rainfall Excess) x (Catchment Area)
    Area under DRH = Area of triangle = 0.5 x Peak Flow (in m3/s) x Time Base (in seconds)
    = 0.5 x 50 x 80 x 60 x 60 = 72 x 105 m3
    Catchment Area = 144 km2 = 144 x 106 m2
    (Area under DRH) = (Rainfall Excess) x (Catchment Area)
    Therefore, Rainfall excess = (72 x 105)/ (144 x 106) = 0.05 m = 5cm
    View all questions of this test
    Most Upvoted Answer
    A triangular DRH due to a storm has a time base of 80 h and a peak flo...
    Free Test
    Community Answer
    A triangular DRH due to a storm has a time base of 80 h and a peak flo...
    To determine the rainfall excess in the storm, we need to calculate the total rainfall and subtract the initial abstraction. Here is the step-by-step explanation:

    1. Calculate the total volume of rainfall:
    Total volume of rainfall = peak flow * time base
    Total volume of rainfall = 50 m3/s * 80 h = 4000 m3

    2. Convert catchment area to square meters:
    Catchment area = 144 km2 = 144 * 10^6 m2

    3. Calculate the average rainfall over the catchment area:
    Average rainfall = Total volume of rainfall / catchment area
    Average rainfall = 4000 m3 / 144 * 10^6 m2 = 0.0278 m or 2.78 cm

    4. Calculate the initial abstraction:
    The initial abstraction is the rainfall that is lost due to interception, depression storage, and other losses before runoff starts. Given that the peak flow occurs at 20 h, the initial abstraction can be calculated as follows:
    Initial abstraction = average rainfall * 20 h
    Initial abstraction = 0.0278 m * 20 h = 0.556 m or 55.6 cm

    5. Calculate the rainfall excess:
    Rainfall excess = Average rainfall - Initial abstraction
    Rainfall excess = 2.78 cm - 55.6 cm = -52.82 cm

    6. Interpretation:
    The negative rainfall excess value indicates that the initial abstraction is greater than the average rainfall. This means that the storm event did not generate enough rainfall to cause runoff, and all the rainfall was lost through interception, depression storage, and other losses.

    However, it is worth noting that the given correct answer is '5' cm, which implies that there might be an error in the calculations or in the given data.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer?
    Question Description
    A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer?.
    Solutions for A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
    Here you can find the meaning of A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer?, a detailed solution for A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? has been provided alongside types of A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A triangular DRH due to a storm has a time base of 80 h and a peak flow of 50 m3/s occurring at 20 h from the start. If the catchment area is 144 km2, then the rainfall excess in the storm is ________ cm.Correct answer is '5'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
    Explore Courses for Civil Engineering (CE) exam

    Top Courses for Civil Engineering (CE)

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev