A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:?
Most Upvoted Answer
A and B can do a piece of work in 45 days and 40 days respectively. Th...
Work Rates of A and B
To solve the problem, we first need to determine the work rates of A and B.
- A can complete the work in 45 days, so A’s work rate is:
**Work rate of A = 1/45 work/day**
- B can complete the work in 40 days, so B’s work rate is:
**Work rate of B = 1/40 work/day**

Total Work Rate Together
When A and B work together, their combined work rate is:
- **Combined work rate = (1/45 + 1/40)**
To add these fractions, find a common denominator (which is 360):
- **Combined work rate = (8/360 + 9/360) = 17/360 work/day**

Work Done by A and B Together
Let’s say A worked with B for **x days**. The work done by both in x days will be:
- **Work done = x * (17/360)**

Remaining Work by B
After A leaves, B finishes the remaining work in 23 days. The work done by B in 23 days is:
- **Work done by B = 23 * (1/40) = 23/40**
The total work done is equal to 1 (the whole work):
- **Work done by A and B together + Work done by B alone = 1**
Substituting the equations gives:
- **(17x/360) + (23/40) = 1**

Solving the Equation
Now, we need to solve for x:
1. Convert 23/40 to a fraction with a denominator of 360:
**23/40 = 207/360**
2. Substitute and rearrange:
**(17x/360) + (207/360) = 1**
**17x + 207 = 360**
**17x = 153**
**x = 9**

Conclusion
A left the work after **9 days**. Thus, A and B worked together for 9 days before A departed, and B completed the remaining work alone in 23 days.
Explore Courses for SSC CHSL exam

Top Courses for SSC CHSL

A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:?
Question Description
A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? for SSC CHSL 2025 is part of SSC CHSL preparation. The Question and answers have been prepared according to the SSC CHSL exam syllabus. Information about A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? covers all topics & solutions for SSC CHSL 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:?.
Solutions for A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? in English & in Hindi are available as part of our courses for SSC CHSL. Download more important topics, notes, lectures and mock test series for SSC CHSL Exam by signing up for free.
Here you can find the meaning of A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? defined & explained in the simplest way possible. Besides giving the explanation of A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:?, a detailed solution for A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? has been provided alongside types of A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? theory, EduRev gives you an ample number of questions to practice A and B can do a piece of work in 45 days and 40 days respectively. They begin to do the work together but A left after some days and then B completed the remaining work in 23 days. The number of days, after which A left the work was.:? tests, examples and also practice SSC CHSL tests.
Explore Courses for SSC CHSL exam

Top Courses for SSC CHSL

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev