Bank Exams Exam  >  Bank Exams Questions  >  A builder hires three different teams of work... Start Learning for Free
A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.
(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.
All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.
When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.
All members of team R can complete the whole job together in (Y + 25) days.?
Most Upvoted Answer
A builder hires three different teams of workers - P [(Z+14) members] ...
Understanding Team Efficiencies
- Team P has (Z + 14) members.
- Team Q consists of [4(Y - 5)] members.
- Team R consists of (3M) members.
Job Completion Rates
- (Z + 6) members of Team P and (Y + 5) members of Team Q can complete the job in M days.
- Team Q's efficiency is twice that of Team R.
Team Job Capacities
- All members of Team P can complete the job in M days.
- All members of Team Q can complete double the job in 3M days.
Work Cycle of Team Q and Team P
- Team Q works every second day:
- After 2M days, they are replaced by Team P.
- Team P completes the remaining work in (2M - Z)/3 days.
Team R's Job Completion Time
- All members of Team R can complete the job in (Y + 25) days.
Key Relationships
- The relationship between team efficiencies is crucial:
- If Team Q is twice as efficient as Team R, their combined rates affect the overall job completion time.
Conclusion
This setup creates a complex interplay between team sizes, efficiencies, and job completion times, illustrating the importance of understanding workforce dynamics in construction projects. By analyzing each team's capabilities and scheduling, the builder can effectively manage the project timeline.
Explore Courses for Bank Exams exam

Similar Bank Exams Doubts

Direction: Study the following information carefully and answer the questions given below:-Nehru, Gandhi and Patel are three adjacent buildings. Nehru building is to the west of Gandhi building, Gandhi building is to the west of Patel building. Each building has a different number of floors with the lowest floor numbered 1, the floor above it as number 2 and so on. The height of the floor in each building is the same i.e. the same numbered floor is at an equal height from the ground. Only a few of the floors of these buildings are taken and rests are vacant. Only one person can live on each floor of each building.Nikhil lived on the floor which was immediately above Shubham’s floor but in a different building. Shubham and Nikhil are in an adjacent building. Shubham was to the west of Sumit. The number of floors in building Nehru was 3 more than Abhay’s Floor number. Abhay was to the west of Amit who lived 2nd from the top of his building. Neeraj was in building Gandhi and the number of floors in his building was twice as that of his floor number. Prashant lived on the floor which was immediately below Pratap’s floor but in a different building. Vishal lived on floor 4 but was not in Prashant’s building. Abhay’s floor number was twice as that of Neeraj’s floor number. Amit and Pratap were not in the same building. No building had more than 10 floors. Neeraj’s floor number was thrice as that of Prashant’s floor number. Amit and Nikhil lived in an adjacent building. Abhay lived on the floor which was immediately above Nikhil’s floor but in a different building. Sumit and Prashant lived in adjacent buildings. Pratap and Shubham lived in different buildings. Prashant lived in Building Nehru.Q. How many vacant floors are there in Building Nehru?

Direction: Study the following information carefully and answer the questions given below:-Nehru, Gandhi and Patel are three adjacent buildings. Nehru building is to the west of Gandhi building, Gandhi building is to the west of Patel building. Each building has a different number of floors with the lowest floor numbered 1, the floor above it as number 2 and so on. The height of the floor in each building is the same i.e. the same numbered floor is at an equal height from the ground. Only a few of the floors of these buildings are taken and rests are vacant. Only one person can live on each floor of each building.Nikhil lived on the floor which was immediately above Shubham’s floor but in a different building. Shubham and Nikhil are in an adjacent building. Shubham was to the west of Sumit. The number of floors in building Nehru was 3 more than Abhay’s Floor number. Abhay was to the west of Amit who lived 2nd from the top of his building. Neeraj was in building Gandhi and the number of floors in his building was twice as that of his floor number. Prashant lived on the floor which was immediately below Pratap’s floor but in a different building. Vishal lived on floor 4 but was not in Prashant’s building. Abhay’s floor number was twice as that of Neeraj’s floor number. Amit and Pratap were not in the same building. No building had more than 10 floors. Neeraj’s floor number was thrice as that of Prashant’s floor number. Amit and Nikhil lived in an adjacent building. Abhay lived on the floor which was immediately above Nikhil’s floor but in a different building. Sumit and Prashant lived in adjacent buildings. Pratap and Shubham lived in different buildings. Prashant lived in Building Nehru.Q. Which floor is occupied by Abhay and in which building?

Direction: Study the following information carefully and answer the questions given below:-Nehru, Gandhi and Patel are three adjacent buildings. Nehru building is to the west of Gandhi building, Gandhi building is to the west of Patel building. Each building has a different number of floors with the lowest floor numbered 1, the floor above it as number 2 and so on. The height of the floor in each building is the same i.e. the same numbered floor is at an equal height from the ground. Only a few of the floors of these buildings are taken and rests are vacant. Only one person can live on each floor of each building.Nikhil lived on the floor which was immediately above Shubham’s floor but in a different building. Shubham and Nikhil are in an adjacent building. Shubham was to the west of Sumit. The number of floors in building Nehru was 3 more than Abhay’s Floor number. Abhay was to the west of Amit who lived 2nd from the top of his building. Neeraj was in building Gandhi and the number of floors in his building was twice as that of his floor number. Prashant lived on the floor which was immediately below Pratap’s floor but in a different building. Vishal lived on floor 4 but was not in Prashant’s building. Abhay’s floor number was twice as that of Neeraj’s floor number. Amit and Pratap were not in the same building. No building had more than 10 floors. Neeraj’s floor number was thrice as that of Prashant’s floor number. Amit and Nikhil lived in an adjacent building. Abhay lived on the floor which was immediately above Nikhil’s floor but in a different building. Sumit and Prashant lived in adjacent buildings. Pratap and Shubham lived in different buildings. Prashant lived in Building Nehru.Q. How many floors are present in all three buildings?

Direction: Study the following information carefully and answer the questions given below:-Nehru, Gandhi and Patel are three adjacent buildings. Nehru building is to the west of Gandhi building, Gandhi building is to the west of Patel building. Each building has a different number of floors with the lowest floor numbered 1, the floor above it as number 2 and so on. The height of the floor in each building is the same i.e. the same numbered floor is at an equal height from the ground. Only a few of the floors of these buildings are taken and rests are vacant. Only one person can live on each floor of each building.Nikhil lived on the floor which was immediately above Shubham’s floor but in a different building. Shubham and Nikhil are in an adjacent building. Shubham was to the west of Sumit. The number of floors in building Nehru was 3 more than Abhay’s Floor number. Abhay was to the west of Amit who lived 2nd from the top of his building. Neeraj was in building Gandhi and the number of floors in his building was twice as that of his floor number. Prashant lived on the floor which was immediately below Pratap’s floor but in a different building. Vishal lived on floor 4 but was not in Prashant’s building. Abhay’s floor number was twice as that of Neeraj’s floor number. Amit and Pratap were not in the same building. No building had more than 10 floors. Neeraj’s floor number was thrice as that of Prashant’s floor number. Amit and Nikhil lived in an adjacent building. Abhay lived on the floor which was immediately above Nikhil’s floor but in a different building. Sumit and Prashant lived in adjacent buildings. Pratap and Shubham lived in different buildings. Prashant lived in Building Nehru.Q. On which floor does Amit lived and in which building?

A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.?
Question Description
A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? for Bank Exams 2024 is part of Bank Exams preparation. The Question and answers have been prepared according to the Bank Exams exam syllabus. Information about A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? covers all topics & solutions for Bank Exams 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.?.
Solutions for A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? in English & in Hindi are available as part of our courses for Bank Exams. Download more important topics, notes, lectures and mock test series for Bank Exams Exam by signing up for free.
Here you can find the meaning of A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? defined & explained in the simplest way possible. Besides giving the explanation of A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.?, a detailed solution for A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? has been provided alongside types of A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? theory, EduRev gives you an ample number of questions to practice A builder hires three different teams of workers - P [(Z+14) members] Q [4(Y-5)] members, and R (3M, members) to construct a building.(Z+6) members of team P and (Y + 5) members of team Q together can complete the job in M days (integer). Each member of team Q is twice as efficient as that of team R.All members of team P together can-do same job in M days, while all members of team Q together can complete twice of job in 3M days.When all members of team Q started the work (such a way that every second day they take rest), after 2M days, team is replaced by team P who complete the remaining work in (2M-Z)/3 days.All members of team R can complete the whole job together in (Y + 25) days.? tests, examples and also practice Bank Exams tests.
Explore Courses for Bank Exams exam

Top Courses for Bank Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev