Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The main object of a preliminary surveya)to c... Start Learning for Free
The main object of a preliminary survey
  • a)
    to collect the necessary physical information and details of topography, drainage anc soil properties.
  • b)
    to estimate cost of alternative alignment.
  • c)
    to finalise the best alignment.
  • d)
    all the above
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
The main object of a preliminary surveya)to collect the necessary phys...
The main objective of a preliminary survey is to minimize the cost of groundwater development. Planning a preliminary groundwater survey includes minimizing the total cost of study and implementation of the groundwater development project.
View all questions of this test
Most Upvoted Answer
The main object of a preliminary surveya)to collect the necessary phys...
Preliminary survey is the first stage in the process of planning and designing of any engineering project. The main objective of a preliminary survey is to collect the necessary physical information and details of topography, drainage and soil properties. Let's discuss this in detail:

Collecting Physical Information:
During the preliminary survey, the engineers collect the physical information about the site such as the location, boundaries, size, and shape of the site. They also collect information about the existing structures, buildings, roads, and other facilities that are present in the area. This information helps the engineers to understand the site conditions and constraints, which are essential for the design of the project.

Details of Topography:
The engineers also collect the details of the topography of the site, such as the elevation, slope, and contours. This information helps the engineers to understand the natural drainage pattern of the site, which is important for the design of the drainage system.

Details of Drainage:
The engineers also collect information about the drainage system of the site, such as the location and size of the rivers, streams, and other water bodies. This information helps the engineers to design the drainage system of the project, which is important for the safety of the project.

Details of Soil Properties:
The engineers also collect information about the soil properties of the site, such as the soil type, bearing capacity, and stability. This information helps the engineers to design the foundation of the project, which is important for the stability of the project.

Conclusion:
Therefore, the main object of a preliminary survey is to collect the necessary physical information and details of topography, drainage and soil properties. This information helps the engineers to understand the site conditions and constraints, which are essential for the design of the project.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer?
Question Description
The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The main object of a preliminary surveya)to collect the necessary physical information and details of topography, drainage anc soil properties.b)to estimate cost of alternative alignment.c)to finalise the best alignment.d)all the aboveCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev