In levelling operationa)The line commences with a fore sight and close...
Before shifting the instrument the last sight is foresight which is taken on change point. After shifting the instrument the first sight taken is taken on the same change point i.e back sight.
View all questions of this test
In levelling operationa)The line commences with a fore sight and close...
In leveling operations, a line is established between two points to determine the difference in elevation between them. This process involves taking measurements using a leveling instrument, such as a level or a theodolite.
The correct answer is option 'c) The line commences with a back sight and closes with a foresight.'
Explanation:
1. Back Sight:
- The back sight is the first reading taken on a point of known elevation, such as a benchmark or a previously established point.
- It is called a back sight because it is taken with the instrument placed at the back of the point.
- The purpose of the back sight is to establish a starting reference point for the leveling process.
2. Intermediate Sight:
- After taking the back sight, the leveling line is extended to the next point.
- The next reading taken on this point is called an intermediate sight.
- The intermediate sight is used to continue the leveling line and determine the difference in elevation between the two points.
3. Change Point:
- The intermediate sight is taken on a change point, which is a point where the elevation changes along the line.
- Change points can be natural features such as ridges or valleys, or they can be man-made features like roads or buildings.
- The purpose of taking an intermediate sight on a change point is to determine the difference in elevation between the two points on either side of the change.
4. Fore Sight:
- After taking the intermediate sight on the change point, the leveling line is extended further to the next point.
- The next reading taken on this point is called a fore sight.
- The fore sight is taken with the instrument placed in front of the point.
- The purpose of the fore sight is to determine the difference in elevation between the change point and the next point.
5. Closing the Line:
- The leveling line continues in this manner, with back sights, intermediate sights, and fore sights, until the desired points are connected.
- The line is closed when a fore sight is taken on the last point, which is typically a benchmark or a known elevation point.
- Closing the line allows for the accuracy of the leveling measurements to be checked and adjusted if necessary.
Therefore, in leveling operations, the line commences with a back sight and closes with a foresight. This sequence of readings ensures that the elevation differences between the points are accurately determined.
In levelling operationa)The line commences with a fore sight and close...
In the first option a:to fix the new station point we need to know the know RL of staff.
option B:to carryout the levelling we need to shift the staff in the line of surveying.
To make sure you are not studying endlessly, EduRev has designed Civil Engineering (CE) study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Civil Engineering (CE).